27th December, 2002
POWER
REPUBLIC DAY 2003


THE TURNAROUND HAS BEGUN

Anant G. Geete*


Power is a critical infrastructure for the country’s economic development. The Ministry of Power has given a major thrust to speed up the development and reforms of the power sector. It has set an agenda for providing power to all by 2012. The Ministry seeks to achieve this objective through a comprehensive and holistic approach to power sector development at the national, state, SEB, distribution, feeder and consumer levels.

To meet the projected power requirement by 2012 an additional capacity addition of 100,000 MW is required in the next two Five Year Plans. A capacity of nearly 41,000 MW would be set up in the 10th Plan and the remaining in the 11th Plan with a stronger focus on hydro power. The Central sector would contribute 22,500 MW, the State sector 11400 MW and the Private Sector 7,100 MW in the 10th Plan. Projects of above 19000 MW are already under construction while projects of 8,900 MW aggregate capacity have been given the requisite approvals. The outlay for the power sector has been raised from Rs.45,591 crore during the 9th Plan to Rs.143,399 crore in the 10th Plan.

The Conference of Chief Ministers in March, 2002 under the chairmanship of the Prime Minister resolved that all villages should be electrified by 2007 and full coverage of households be achieved by 2012. Rural electrification is now treated as a basic minimum service under the "Pradhan Mantri Gramodaya Yojana" (PMGY) from 2001-02. It is proposed to cover all the 62000 villages that can be electrified through grid connectivity during the 10th Plan. The balance 18,000 remote villages are to be electrified through the use of non-conventional technologies.

Power generation resources are unevenly distributed in the country. The Hydro resources are mainly located in the Himalyan region and coal, the basis of thermal power in eastern and central parts of the country. Optimum and economic utilization of these resources require inter-regional transmission of power from generation centers to load centers. The concept of a strong inter-connected National Power Grid across the country is, therefore, of crucial significance. The present inter-regional power transfer capacity of about 5000 MW will be enhanced to 8000 MW by December, 2002 and 23,500 MW by the end of the 10th Plan.

Reforms

Reforms in the power sector were initiated in 1991 by liberalizing generation. It is clear that a commercially viable distribution is necessary to sustain investment in generation and transmission. For attaining this objective, comprehensive reforms of the State Electricity Board (SEBs) have been undertaken. The SEBs of Orissa, Haryana, Andhra Pradesh, Karnataka, Rajasthan, Uttar Pradesh, Madhya Pradesh, Uttaranchal and Delhi have been unbundled. Power distribution has been privatized in Orissa and Delhi. To rationalize the tariff fixation mechanism, the Central Electricity Regulatory Commission (CERC) has been set up by the Union Government and State Electricity Regulatory Commissions (SERCs) have been set up in 21 States. The SERCs of 13 States have issued tariff orders.

Even though distribution of power is a state function, the Ministry of Power has taken a pro-active role to modernize and strengthen the distribution system. The Central Government launched the Accelerated Power Development Programme in 2001-02 with an outlay of Rs.1000 crore. It has been re-designated as Accelerated Power Development and Reform Programme from the current financial year with an outlay of Rs.3,500 crore. The scheme, besides providing support to the States for investment in sub-transmission and distribution will also have a reward component for States which have been able to reduce the gap between unit cost of supply and realization. The emphasis of distribution reforms is on achieving metering of all 11 KV feeders, 100 per cent metering of all consumers, reduction of T&D losses and control of theft to ensure quality supply of power to all consumers.

The Ministry of Power has signed MOUs/MOA with 24 States to expedite the process of reforms. The MOUs provide for metering of all 11 KV feeders, 100 per cent metering of consumers, energy audit, reduction of T&D losses and attaining the commercial viability in distribution.

Due to poor financial health, a number of the SEBs defaulted on their payment to power generating companies, coal suppliers and railways. The cumulative amount due to these agencies from the SEBs exceeds Rs.41,000 crore, seriously impacting the borrowing capacities of the SEBs. A scheme of one-time settlement of outstanding dues has been formulated to wipe out the entire outstanding dues. Nineteen States have accepted the scheme and signed the requisite Tripartite Agreement.

The project clearance process has been simplified. The private sector can now participate in generation, transmission and distribution of power. Automatic approval for 100 per cent foreign equity was permitted for foreign investment upto Rs.1,500 crore. This ceiling has been removed since June, 2000. Captive power projects costing less than Rs.3000 crores and supplying less than 50 per cent of the installed capacity to the grid have been exempted from the requirement of clearance of the CEA. Similarly, for any generating project costing less than Rs.2,500 crore, where the tariff is approved by the Regulatory Commissions, the requirement of techno-economic clearance of CEA has been dispensed with. For speedy clearance of the central sector hydro power schemes, a three stage clearance procedure has been adopted.

To provide for a liberalized framework, a comprehensive Electricity Bill, 2001 was introduced in the Lok Sabha in August, 2001. The Bill provides for delicensing of generation, non-discriminatory open access in transmission, power trading, rural electrification, mandatory requirement of SERCs, mandatory metering and stringent provisions against theft of power.

The Power Trading Corporation (PTC) has been set up. Trading activities of PTC have already started from surplus regions to deficit regions. The trading volume went up to 1,617 million kwh during 2001-02.

To achieve a broad consensus and general awareness among the public on the need for reforms in the power sector and also to share with opinion leaders, students and the general public more than 2085 road shows were organized by the Ministry of Power and its CPSUs in 2001-02.

The Energy Conservation Act, 2001 has been enacted to provide for efficient use of energy and its conservation. The Bureau of Energy Efficiency (BEE) has been set up and the Hon’ble Prime Minister released its action plan on August 23, 2002. (PIB Features)

*Union Minister of Power

 
[previous feature] [next feature]
 
Home
Press Releases

English Reases
Hindi Releaelses
Urdu releases
Ministrywise Releases

Photogallery
  Today's Photogallery
Photo Archives
Features
English Features
Hindi Features
PIB
  Contact Information
About us
Subscribe PIB Releases
Accredited Journalists
Important Links
Pesident's Office
Prime Minister's Office
Indian Parliament
Media Units
DD News
AIR News
GOI Website Directory
   
Site Content Administered by :
Senior Additional Principal Information Officer
Press Information Bureau
"A" - Wing, Shastri Bhawan,
Dr. Rajendra Prasad Road,
New Delhi - 110 001