Status of Work in GCNEP

Phase–I of the project titled “Establishment of Global Centre for Nuclear Energy Partnership (GCNEP)” at Kheri Jasaur, near Bahadurgarh, Haryana has been completed.

30th September 2020 is the date of Phase –II of the project.

₹142 crore  for  Phase – I, which  has  been  completed  in  March, 2017.  Total sanctioned cost for completion of Phase –II is ₹ 811 crore.

The details of CSR activities started/planned at Jasaur Kheri or nearby areas are as follows:-

As a part of CSR activities, DAE has agreed to make a contribution of  ₹ 10 crore.

As a part of the above commitments, DAE has so far released the following funds:-

₹ 1 crore for Government Girls College at Jasaur Kheri (Jhajjar).

₹ 1 crore for two Computer Training Centres, one at Bahadurgarh and other at Islamgarh (Chhuchhakwas).

₹ 20 lakh for two Common Service Centre, one at Mini Secretariat, Bahadurgarh and other at Mini Secretariat, Beri.

This was stated by the Minister of State in Ministry of Personnel, PG & Pension and in the Prime Minister’s Office, Dr. Jitendra Singh in a written reply to question in the Lok Sabha today.

 

****  