Production Performance of Crude Oil & Natural Gas Sector For the Month of July 2012

A. CRUDE OIL PRODUCTION  – PERFORMANCE

Month / Period

Planned Target (TMT)

Actual Production (TMT)

%age achievement

Surplus(+) Shortfall(-) Vis-à-vis target (%age)

Surplus(+) Shortfall(-) over last year   (%age)

July, 2012*

3371.367

3256.431

96.6

-3.4

-0.6

April-July, 2012*

13131.583

12789.728

97.4

-2.6

-0.6

April-July, 2011

 

12863.099

 

 

 

TMT: Million Metric Tonnes.

*: Provisional.

B. COMPANY-WISE ACHIEVEMENT

Company / State

Planned Target (TMT)

Actual Production (TMT)

%age achievement

Surplus(+) Shortfall(-) (%age)

ONGC

2005.400

1910.100

95.2

-4.8

  Gujarat

454.000

446.000

98.2

 

  Andhra Pradesh

23.000

25.000

108.7

 

  Tamil Nadu

18.000

21.000

116.7

 

  Assam

101.000

104.000

103.0

 

  Tripura

0.4000

0.1000

25.0

 

  Mumbai Region   (incl Mumbai High)

1409.000

1314.000

93.3

 

OIL

333.500

325.500

97.6

-2.4

  Assam

331.500

323.700

97.6

 

  Arunachal Pradesh

2.000

1.800

90.0

 

PRIVATE/JVC

1032.467

1020.831

98.9

-1.1

TOTAL

3371.367

3256.431

96.6

-3.4

C. REASONS FOR SHORTFALL

Company / State

Reasons for shortfall

ONGC (Gujarat)

Poor Influx & Power shutdown.

ONGC (Mumbai High Offshore)

Less than anticipated oil gain from development and side track wells.   Closure of wells due to low availiability of gas for gas lift. Production affected due to increasing water cut, less than anticipated oil gain from Vasai East. Less line condensate receipt from offshore. 

OIL (Assam & Arunachal Pradesh)

Several OIL Blockades by various Groups during the month of July, 2012 and frequent miscreants activities in the fields.

Pvt./JVCs  ( Arunachal Pradesh)

Water/sand ingress in wells and underperformance of newly drilled wells.

Pvt./JVCs ( Western Offshore-Panna-Mukta)

Lower oil production due to delay in well intervation jobs, unplanned shutdown and underperformance of MA # 4 & # 8 wells.  NANG production is nil due to ceasing of PG.

A statement showing Crude Oil Production during July, 2012 and cumulatively for the period April- July, 2012 vis-à-vis 2011-12 planned production is at Annexure-I 

II.  A. REFINERY PRODUCTION

    (IN TERMS OF CRUDE THROUGHPUT)

Month / Period

Planned Target (MMT)

Actual Production (MMT)

%age achievement

Surplus(+) Shortfall(-) Vis-à-vis target         (in %age)

Surplus(+) Shortfall(-) over last year          (in %age)

July, 2012*

14.898

14.984

100.6

0.6

3.6

April- July, 2012*

57.921

58.844

101.6

1.6

3.3

April- July, 2011

 

56.942

 

 

 

*: Provisional.

The crude throughput in IOC (Barauni, Koyali, Mathura, Digboi  & Bongaigaon), BPCL (Kochi), HPCL (Mumbai), CPCL (Manali), MRPL (Mangalore), RIL (Jamnagar) & Essar Oil Ltd. Vadinar refineries have exceeded their planned target.

The crude throughput in  IOC (Guwahati, Haldia & Panipat), BPCL (Mumbai), BORL (Bina), HPCL (Visakh), CPCL (Narimanam), NRL (Numaligarh), & ONGC Tatipaka  refineries was less than their planned target.

B. REASONS FOR SHORTFALL :

Company / State

Reasons for shortfall

IOC (Panipat)

Throughput  marginally lower than OIE target in view of high intermediate stock.

IOC (Haldia)

Throughput is restricted due to interruption in OHCU operation.

IOC (Guwahati)

Throughput marginally lower due to deferment of planned M&I shutdown from June' 12 to July' 12.

BORL, Bina

Capacity utilization was lower due to two number of power interruptions during July'12.

HPCL, Visakh

●   Throughput lower than the MOU excellent Target due to deferment of planned CDU-III shutdown from May-June' 12 to July-August'12.

A statement showing refinery-wise production during the month of July, 2012 and cumulatively for the period April- July, 2012 vis-à-vis 2011-12 planned target is at Annexure-II.

III.  REFINERY CAPACITY UTILISATION [excluding RPL(SEZ)]

Month

Utilisation (%)

Period

Utilisation (%)

 July, 2012*

110.0

April- July, 2012

99.4

 July, 2011

109.9

April- July, 2011

106.5

The refinery-wise details of the capacity utilisation during July, 2012 and cumulatively for the period April- July, 2012 vis-a-vis 2011-12 are given in Annexure-III.

 

IV.        A.  NATURAL GAS PRODUCTION

Month / Period

Planned Target (MCM)

Actual Production (MCM)

%age achieve-ment

Surplus(+) Shortfall(-) Vis-à-vis target    (%age)

Surplus(+) Shortfall(-) over last year     (%age)

July, 2012*

3520.540

3577.074

101.6

1.6

-13.6

April- July, 2012*

13620.093

14439.008

106.0

6.0

-11.7

April- July, 2011

 

16356.262

 

 

 

MCM: Million Cubic Metres.         

*: Provisional.

B.     COMPANY-WISE ACHIEVEMENT

Company / State

Planned Target (MCM)

Actual Production (MCM)

%age achievement

Surplus(+) Shortfall(-) (%age)

ONGC

2038.451

1976.658

97.0

-3.0

  Gujarat

118.283

155.512

131.5

 

  Rajasthan

1.258

1.442

114.6

 

  Andhra Pradesh

88.510

109.240

123.4

 

  Tamil Nadu

118.869

83.506

70.3

 

  Assam

38.627

41.508

107.5

 

  Tripura

78.280

48.489

61.9

 

  Mumbai High Offshore

1594.624

1536.961

96.4

 

OIL

244.800

226.930

92.7

-7.3

  Assam

223.600

204.950

91.7

 

  Arunachal Pradesh

1.500

1.240

82.7

 

  Rajasthan

19.700

20.740

105.3

 

PRIVATE/JVC

1237.289

1373.486

111.0

11.0

  Onshore $

12.237

67.477

551.4

 

  Offshore

1225.052

1306.009

106.6

 

TOTAL

3520.540

3577.074

101.6

1.6

$: Including Coal Bed Methane production.

C.     REASONS FOR SHORTFALL

Company / State

Reasons for shortfall

ONGC (Tripura)

Less offtake by consumers.

ONGC (Tamilnadu)

Less offtake by consumer M/s. TNEB

ONGC (Mumbai High Offshore)

Closure of wells for buildup study. Delay in Project execution of G-1 field.

OIL (Assam & Rajasthan)

Less gas production and sale was due to bandhs/blockades by various organisation and less than the committed withdrawal by customers.

A statement showing natural gas production during July, 2012  and cumulatively for the period April- July, 2012 vis-à-vis 2011-12 is at Annexure-IV.

Click here to see Annexure

Note: Totals may not tally due to rounding off figures.

RCJ/RKS