The
Union Minister of State for Power, Shri K.C.Venugopal,
informed Lok Sabha today in
a written reply that power
generation targets (in Million Units) are fixed on an annual basis and not for
a Five Year Plan period. However, the
Plan-wise capacity addition target set (in MW) and achievement made during the last
three plan periods are indicated as below:
|
Five Year Plan
|
Target(MW)
|
Achievement(MW)
|
|
9th (1997-2002)
|
40245
|
19,015
|
|
10th (2002-2007)
|
41110
|
21180
|
|
11th (2007-2012)
|
78700
|
54964
|
The
power generation capacity added in the Eleventh Plan is 54964 MW as against the
total capacity addition of 56618 MW in the 8th, 9th and
10th Plans taken together.
The capacity added during the Eleventh Plan is about 260% of the total
capacity added during the Tenth Plan. In
the year 2011-12, capacity addition of 20502 MW exceeded the target of 17601
MW, which is the highest ever annual capacity addition and is nearly equal to
capacity added in the Tenth Plan.
The
major reasons for not achieving the capacity addition targets include delay in the placement of orders for
main plant equipment, delay and non-sequential supply of material for main
plant and Balance of Plant, slow progress of civil works, contractual disputes
between project developer and contractor and their sub-vendors /
sub-contractors, poor geology, flash
flood, delay in land
acquisition, environmental concern, shortage of manpower, law and order
problems and difficult climate conditions.
The
Working Group on Power constituted by the Planning Commission to formulate the
12th Five Year Plan for the Power sector has submitted it’s report to the Planning Commission. As per the report of
this Working Group, capacity addition requirement during the 12th
Plan is 75,785 MW. The source-wise break up of 12th Plan capacity
addition programme is given as under:
(In
MW)
|
|
Hydro
|
Thermal
|
Nuclear
|
Total
|
|
|
|
Central
|
5632
|
11426
|
2800
|
19858
|
|
|
State
|
1456
|
12340
|
0
|
13796
|
|
|
Private
|
2116
|
40015
|
0
|
42131
|
|
|
Total
|
9204
|
63781
|
2800
|
75785
|
|
The
Minister further informed that several measures have been initiated by the
Government to achieve the capacity addition target. These include:
(i)
Augmentation
of manufacturing capacity of BHEL from 10,000 MW in December, 2007 to 20,000 MW
by 2012.
(ii)
Formation
of several new joint ventures to manufacture super-critical boilers and
turbine-generators for thermal power plants.
(iii)
Periodic
review of issues related to supply of power equipment from BHEL by a group
under the chairmanship of Secretary (Heavy Industry).
(iv)
Rigorous
monitoring of projects at different levels including by Ministry of Power,
Central Electricity Authority, Power Projects Monitoring Panel and Advisory
Group under the chairmanship of Minister of Power.
UM/ska