The Government accorded approval for undertaking six
laning of 6,500 km of National Highways comprising 5,700 km of Golden Quadrilateral
and balance 800 km on other sections, under National Highways Development Project
(NHDP) Phase-V. As per the approved
implementation mechanism for NHDP Phase-V, stretches of 100 km or more that have
been completed at least two years ago and contractual actions on previous contracts
have been completed, are being included in the year-wise programme.
Where the distance between two cities is less than 100 km, such stretches
are also being included as exception cases.
Cost per km has been estimated as Rs. 6.34 crore.
List
of proposed stretches of National Highways in different states under NHDP Phase-V
is given below: SIX LANING OF NATIONAL HIGHWAYS
| Stretches |
States |
Length (in km) | |
(a) Golden Quadrilateral | Andhra
Pradesh, Bihar, Gujarat, Haryana, Karnataka, Maharashtra, Orissa, Rajasthan, Tamil
Nadu, Uttar
Pradesh, West Bengal and Jharkhand. | 5700 |
|
(b) Other Stretches | | | |
(i) Panipat-Jalandhar | Haryana
and Punjab | 300 |
|
(ii) Delhi-Hapur-Moradabad | Delhi
and Uttar Pradesh | 170 |
|
(iii) Samkhiali-Gandhidham | Gujarat | 56 |
|
(iv) Indore-Dewas | Madhya
Pradesh | 55 |
|
(v) Agra-Gwalior | Uttar
Pradesh and Madhya Pradesh | 85 |
|
(vi) Chandikhol-Paradeep | Orissa | 77 |
|
(vii)
Ludiana-Chandigarh | Punjab | 82 |
Feasibility
report for seven stretches have been completed by the technical consultants and
detailed is given below: STATUS OF FEASIBILITY REPORT FOR SEVEN STRETCHES UNDER NHDP PHASE-V. | Sl. No. |
Stretch |
NH No. |
Length (in km) |
Cost per km (in crore) | |
1 | Panipat-Jalandhar | 1 | 291.100 | 7.55 |
|
2 | Gurgaon-Kotputli-Jaipur | 8 | 225.600 | 6.72 |
|
3 | Surat-Dahisar | 8 | 239.000 | 5.67 |
|
4 | Chilkaluripet-Vijayawada | 5 | 82.500 | 6.55 |
|
5 | Chennai-Tada | 5 | 43.400 | 7.71 |
|
6 | Chandikhole-Jagatpur-Bhubaneswar | 5 | 67.000 | 15.39 |
|
7 | Delhi-Hapur | 24 | 52.000 | 10.36 |
Total 203 firms
have applied for pre-qualification for eight stretches under NHDP Phase-V. NHDP
Phase-V is scheduled for completion by December, 2012. Estimated civil construction cost for Gurgaon-Kotputli-Jaipur
of 225 km is Rs. 1517 crores. The likely time period for completion is 30 months from the appointed
date. This
information was given by the Minister
of State for Shipping, Road Transport and Highways, Shri K.H. Muniyappa in a written
reply in the Rajya Sabha today.
VBA/BS
|