Friday, August 31, 2007
Ministry of Railways
 

Udhampur-Srinagar-Baramulla Railway Project
17:17 IST

Railways’ ambitious project to connect Kashmir valley to rest of India through Udhampur-Srinagar-Baramulla railway track is going to cost more than what was estimated earlier. The rough estimated cost at the time of preparation of project report was assessed as Rs. 3077 crore. Now the cost has been estimated as Rs. 11,270 crore after completion of detailed engineering survey. Earlier, estimate was prepared on the basis of topo sheets and aerial photographs as detailed survey could not be completed due to highly difficult inaccessible terrain and adverse conditions/situation of the area.

An outlay of Rs. 1700 crore has been proposed as an additonality during 2007-08 and an expenditure of Rs. 3836 crore has been incurred upto March 2007. The project is proposed for completion as per following schedule:-

Udhampur-Katra ---- December, 2008

Katra-Qazigund-----  2011-12

Qazigund-Baamulla—May, 2008

This information was given by the Minister of State for Railways Shri R.Velu in written reply to a question in the Rajya Sabha today.

AKS/HK

 

 
 
Categorized Search
  Handouts
  Photo
      Freedom Movnt
      Photo-divi
  AV/Webcast
Home
Press Releases
English Releases
Hindi Releases
Urdu releases
Ministrywise Releases
Photogallery
  Today's Photogallery
Photo Archives
Features
English Features
Hindi Features
PIB
  Contact Information
About us
Subscribe PIB Releases
Accredited Journalists
Important Links
President's Office
Prime Minister's Office
Indian Parliament
Media Units
DD News
AIR News
GOI Website Directory
   
Press Information Bureau
"A" - Wing, Shastri Bhawan,
Dr. Rajendra Prasad Road,
New Delhi - 110 001